9. Preparation of master manufacturing procedures: The manufacturing procedure
includes manufacturing directives, sampling directions, weight sheet, finished and
in-process product specifications. This section is related with the manner of
presentation of manufacturing procedures which helps in facilitating easy
compliance and understanding of processing technicians.
10. Product stability and uniformity: Each pilot-plant batch should be studied for
stability. The physical, as well as chemical stability studies, should be performed
on pilot-plant batches. The stability studies of finished packages should be carried
11. Good Manufacturing Practices (GMP) Considerations: This section includes the
following items of GMP that are to be considered while the pilot-plant or scale-up
iii. Regularly scheduled preventative maintenance
iv. Regular process review and revalidation
v. Relevant written standard operating procedures
vi. The use of competent, technically qualified personnel
vii. Adequate provision for training of personnel
viii. A well-defined technology transfer system
ix. Validated cleaning procedures
x. An orderly arrangement of equipment for easy material flow and prevention
12. Transfer of analytical methods to quality assurance: In research, all analytical
methods must be transferred to the quality assurance department during the
scale-up of new product. The quality assurance staff should review the process
and make sure that (a) the proper analytical instrumentation is available and (b)
that personnel are trained to perform the tasks.
PILOT-PLANT SCALE-UP CONSIDERATIONS FOR SOLIDS (TABLETS)
The main responsibility of the pilot-plant scale-up is to make sure that the newly
formulated dosage form developed by product development personnel will prove to be
efficiently, consistently and economically reproducible on large-scale production also.
on the ground floor which will help in the expedition of delivery and shipments of
measures should be taken to avoid any extraneous and microbial contamination. These
measures will include the following:
i. Fluorescent lighting fixtures should be of ceiling flush type.
ii. Air-conditioned and humidity-controlled area should be there.
iii. The installation of the high-density concrete floor should be there.
iv. The wall in the processing area, as well as packaging area, should be of enamel